Vassbygdi · Aurland · Vestland, Norway
Vassbygdevegen 19, 5745 Aurland · gnr. 15 / bnr. 15 60.87327° N, 7.32016° E
The site has about 3 MW today. Anything more goes through Sygnir, the local grid company.
| Size | What it likely takes | Cost | Time |
|---|---|---|---|
| ≈3 MW | Today's connection | In place | Now |
| 10–20 MW | A ≈2.5–3 km cable from Sitjande and more transformer capacity, if the 66 kV network has room | ≈€3–5m | 2–3 years |
| 20 MW + | A 420/66 kV transformer at Aurland 1, likely shared with other new load | +≈€6–9m | 3–5 years |
Flåm's 16 MW comes first on the same 35 MVA network, so even 10–20 MW may need the Aurland 1 transformer. Only Sygnir can confirm.
More speed on an existing line is usually a service change that takes weeks. A second, separate route is the bigger job.
| Route | Length | Cost | Time |
|---|---|---|---|
| To Låvi | ≈5.6 km | ≈€0.2–0.5m | 3–9 months |
| To Aurlandsvangen | ≈9.6 km | ≈€0.35–0.8m | 3–9 months |
Costs and times are rough estimates from public benchmarks (Statnett, Nkom), not quotes. Grid and fibre pins are approximate. Distances are straight lines unless marked as road. Prepared 23 October 2026. Sources: Statnett, Aurland 1 application (2021) · NVE decision, Aurland 1 (2022) · Statnett, Aurland–Sogndal 420 kV · Sygnir, Flåm shore power · Map © Kartverket, CC BY 4.0.